← Back to Menu

NPG Production System

中文StationsDashboardReportsData QueryLabels

生產總覽 Production Overview 區間 07:00 換日;「目前 WIP」為即時值,「期初/期末 WIP」依篩選日期回推(已納入盤點調整)

Quick:Last 7 daysLast 4 weeksThis month
Interval:DayWeekMonthYear(affects the trend chart below only)
0
區間出站作業量(各站加總) Out qty in range (sum of all stations)
0
區間報廢 Scrap in range
92
目前在製 WIP(即時) Current WIP (real-time)
25
目前 FG 在庫(即時) Current FG on-hand (real-time)

各站進出 Matrix(區間合計,已扣調整/歸零列) Per-Station In/Out Matrix (range total, net of adjustment/zero-out rows)

站別 Station區間進站 In (range)區間出站 Out (range) 期初 WIP期末 WIP 目前 WIP(即時) Current WIP (real-time)
Charge0
Molding 0 0 0 0
尚無盤點紀錄
0
Deflash 0 0 0 0
最近盤點:07/01
0
FRAME FQC 0 0 57 57
尚無盤點紀錄
57
FRAME Inventory 0 0 10 10
尚無盤點紀錄
10
Overmolding 0 0 0 0
尚無盤點紀錄
0
NPG FQC 0 0 0 0
尚無盤點紀錄
0
Inventory 0 0 25 25
尚無盤點紀錄
25

Processed Quantity by Period

Download CSV
Metric Forming PAMing Press Deflash FRAME FQC Overmolding Final Inspection Total
# of Parts Processed 00000000
Good Parts Out 00000000
Failed Quantity 0000000
Yield
Data sources (07:00 business-day cutover, same date range as this page):
Forming — Processed = Good = kits recognized at coil change ("convert from spool change"; forming_spool, coil ended in range). Failed not tracked at Forming (N/A); Yield shown as —. A coil still in use at range end is not yet counted.
PAMing — Good = Charge station out (item_process, process_station='Charge'). Failed = Charge scrap pieces ÷ 5, rounded down (charge_scrap_log records pieces; 5 pcs = 1 part). Processed = Good + Failed.
Press — Good = Molding station out, good qty (mfg_move station='Molding'). Failed = Molding lost_qty + fail_qty.
Deflash — Good = Deflash station out, good qty. Failed = Deflash lost_qty + fail_qty.
FRAME FQC — Good = FRAME FQC station out. Failed = FRAME FQC fail_qty (fail only; lost excluded).
Overmolding — Good = Overmolding station out (OM vendor return, good). Failed = Overmolding lost_qty + fail_qty.
Final Inspection — Good = NPG FQC out_qty (PASS only). Failed = NPG FQC lost_qty + fail_qty.
Total — row-wise sum across all workcenters (Forming Failed N/A counted as 0); Yield = Total Good / Total Processed. Adjustment/zero-out rows (note 調整/歸零) are excluded from Good throughout.

出站趨勢(依日,各站 07:00 換日) Out Trend (daily, per-station 07:00 rollover)

機台×班別 產出(Molding 良品) Output by Machine × Shift (Molding good qty)

No Molding output data in this range

Shot 投入 vs 產出缺口 Shot Input vs Output Gap(by prod date; gap = input - output; same-day gap is normal before settlement)

Same basis as dashboard: station-out figures net of "adjustment/zero-out" rows; WIP / FG on-hand are real-time cumulative values, unaffected by the date filter above.